Scott Wilson Group plc » Projects » Natural Resources » Energy & Power » Scout Moor Windfarm - Geotechnical Services

Scout Moor Windfarm - Geotechnical Services

Browser does not support script.

Project Introduction

In September 2005, Scott Wilson was commissioned as Lead Design Consultant for Phase 1: Conceptual Design and the subsequent Phase 2: Detailed Design and Construction on the Scout Moor Wind Farm project.

Project Background

The project, to be constructed north of Rochdale, will form part of the growing network of renewable energy resources in the UK and will have a potential output capacity of 65 MW to be supplied directly to the National Grid. The project forms a component of the government’s initiative to increase wind energy to 10% of the UK’s energy supply by 2010. The estimated overall cost of the scheme is £47m. This will include 26 wind turbines, 12km of access track, cable runs and associated structures, two metmasts and a sub-station.

Project Scope

The scope of works included the design of access roadways, turbine and crane pad foundation design, design information for mechanical and electrical consultant; advice on the construction programming and input to the tender package. A major intrusive ground investigation was designed by the geotechnical team and carried out in part by Ground Solutions Group. The £250,000 investigation was designed to confirm the extent of key risk items and to facilitate the design of engineering solutions. Construction commenced during Summer 2006, under the supervision of Scott Wilson.

Value Adding Project Achievements

The key geotechnical issue for the turbines was the extensive un-recorded shallow coal workings in the area. Investigation including trial pits and coring at each location, aerial photographic interpretation, desk studies and geomorphological mapping of adits, shafts and seams throughout the site. The adopted solution was drill and gout for the high and medium risk locations. 

The investigation information was also used to establish foundation solutions for the substantial turbine loads. 

Other geotechnical issues included:

  • Aggressive ground properties in acidic peat.
  • Suitability for re-using arisings elsewhere in the works.   

Related Services

Go

 

View all Services

Find Projects

Sector

Sub Sector

Country

Project Name

Go

 

Contact